Overview
The Projects Overview report brings together project status, timing, risk, and value so you can decide where your team needs to focus.
For onboarding managers, project managers, and Professional Services leaders, it helps answer one core question:
Are our onboarding projects on track, and where do we need to step in?
Start with the summary cards to understand your portfolio, use the charts to identify upcoming commitments and concentrations of risk, and review the drilldown for the project-level context behind those signals.
Filter the report
Use filters to focus on the customers, project managers, work, or time periods relevant to your review.
Filter | When to use it |
Customer | Prepare for a customer check-in or review projects associated with a particular account. |
Project Manager | Focus on projects associated with a particular project manager. |
Brands | Review projects associated with a particular brand. |
Project/Task Custom Fields | Narrow results using information your organization tracks, such as region, onboarding type, customer segment, or purchased products. |
Project Status | Focus on projects in the Pending, In Progress, Done, Late, Cancelled, or On Hold category. |
Task Status | Apply task-status criteria, such as reviewing work marked Stuck, Done, or Not Applicable. |
Project Tags | Focus on projects associated with particular tags. |
Task Tags | Apply criteria based on tags associated with tasks. |
Project Start Date | Review projects by their start-date range. |
Project End Date | Review projects by their end-date range. |
Project Forecasted End Date | Focus on projects with forecasted finish dates in a particular period. |
Task Start Date / Due Date | Apply criteria based on when tasks are scheduled to start or are due. |
For example, an onboarding leader preparing for a delivery review could filter by Project Manager, then use Project Forecasted End Date to focus on upcoming expected finishes.
Choose date filters carefully. When a project starts, when it is due, and when it is forecasted to finish answer different questions.
Note: Not Applicable is a task status, not a project status.
Understand project volume and workload
The volume cards help you distinguish overall project inventory from active work, completed work, and project starts.
Card | What it shows | How to use it |
Projects Created | Projects across all statuses. | Understand overall project volume without assuming every created project has already kicked off. |
Total Active Projects | Projects in In Progress, Late, or On Hold. | Review the portfolio that still needs delivery oversight, including paused work. |
Completed Projects | Projects in the Done category. | Review completed project volume. |
Projects Started This Year | Projects with start dates in the current calendar year. | Review annual project intake using start dates rather than creation or kickoff timestamps. |
The creation, completion, and annual-start cards use different inclusion rules; they should not be treated as interchangeable measures of workload.
Understand what “active” includes
Total Active Projects includes On Hold projects. It excludes projects in Pending, Done, and Cancelled.
The same active-project scope applies to the active status and RAG charts, the forecasted-late and ahead-of-schedule cards, the quarterly forecast, and the top-10 stuck-project view.
“Active” therefore does not mean every included project is currently progressing. It includes paused projects that still require oversight.
To review work without paused projects, use Project Status to focus on In Progress and Late.
Task-based widgets can use different exclusions. See Overdue Tasks by Project below for an important exception.
Review schedule risk
The schedule-risk cards help you distinguish a project’s reported status from its expected finish.
Card | What it tells you | What to investigate next |
Late Projects | Counts projects in the Late status category. | Review the status explanation, project dates, and outstanding work before deciding on a recovery action. |
Projects Forecasted Late | Highlights active projects expected to finish late. | Compare the due date with the forecasted end date and review the work that may affect the finish. |
Projects Ahead of Schedule | Highlights active projects expected to finish earlier than planned. | Confirm that remaining work and customer readiness support an earlier finish before changing commitments. |
Late Projects is status-based; it is not simply a count of projects whose due dates are in the past.
A forecast is a planning signal, not a completed outcome. Use it to start a conversation about the remaining work rather than treating the expected finish as a guarantee.
Plan for upcoming finishes
Projects Due This Month
Question it answers: Which project deadlines should we review this month?
Use Projects Due This Month to focus on projects due during the current month.
This is useful when preparing for final approvals, customer training, implementation handoffs, and go-live readiness. Review the remaining work before treating a scheduled finish as a confirmed delivery commitment.
Quarterly forecast by week
The Projects Forecasted To Finish In The Quarter By Week Break By Status chart groups active projects by forecasted finish week within the current quarter and by current status.
Use it to identify weeks with several expected finishes and prepare the people involved in those handoffs.
For example, several implementations approaching go-live in the same week may require coordination across training, final validation, and the team receiving the customer after onboarding.
Review the status breakdown alongside the expected finish dates. An on-hold project may require a restart conversation before its forecast becomes a useful planning commitment.
Compare project status and health
The status charts help you see how projects are distributed across the portfolio.
Chart | What it shows | When to use it |
Projects by Status | All projects grouped by current status. | Review the overall mix of project work. |
Active Projects by Status | The active portfolio grouped by current status. | Focus on work that still needs oversight, including on-hold projects. |
Active Projects by RAG Status | The active portfolio grouped by RAG health status. | Identify health assessments that deserve a closer review. |
These are views of current status, rather than a history of every status change.
Understand RAG status
RAG stands for Red, Amber, and Green. Green indicates that a project is on track, Amber identifies warning signs, and Red indicates that it is off track. RAG is available in GUIDE 2.0 for internal users and is hidden from customer users. GUIDEcx Knowledge Base
When reviewing RAG results, consider the RAG Description and RAG Updated At information alongside the project’s dates and status.
Use the health assessment to decide where to investigate, then review the project’s circumstances before choosing an action.
Review project duration and intake trends
Average Project Duration
Question it answers: How long do completed projects typically span?
Average Project Duration averages the start-to-end durations of Done projects. GUIDEcx Knowledge Base
Duration is measured in working days, using the working-day settings configured at the workspace level. Do not assume every workspace follows a Monday–Friday schedule.
Use the average as context when planning future onboarding timelines. Compare similar implementations rather than using one portfolio-wide average as the expected duration for every project.
Year-to-date duration by project manager
Avg Project Duration by PM (YTD) provides a year-to-date duration view grouped by project manager.
Use it to prepare coaching, delivery, or resourcing conversations. Compare managers working on similar types of projects before drawing conclusions.
A longer average may warrant investigation, but it does not establish the cause. Review differences in project scope, customer readiness, and delivery complexity before treating the chart as a performance ranking.
Project starts over the last 12 months
Projects Started By Month Break By Status Last 12 Months groups projects by start month and shows their current status, not their historical month-end status. GUIDEcx Knowledge Base
Use it to compare intake patterns and investigate groups of projects that started around the same time.
For example, a particularly busy intake month may be worth reviewing to understand whether the projects that began then need additional delivery support. Consider expected project length and scope before interpreting unfinished work as a problem.
Compare planned and forecasted timing
When investigating schedule movement, review Due Date and Forecasted End Date together.
Use the duration and variance fields in the drilldown as supporting context. When communicating a concern, include the relevant dates and remaining work rather than quoting a duration or variance value on its own.
Understand project value
Cash Value is a field populated by a user or by automation, depending on your organization’s configuration.
Interpret it according to what your organization records in that field. Do not assume it always represents contract value, invoiced revenue, recognized revenue, or cash collected.
The value-focused cards and charts support different questions:
Card or chart | Question to explore | How to use it |
Average Cash Value | What is the average recorded project cash value? | Add value context to a discussion about project volume and project mix. |
Total Cash Value | How much recorded cash value is represented? | Review the financial scale of the projects being evaluated. |
Revenue by Status | How is the reported revenue measure distributed across project statuses? | Investigate whether significant value is associated with work that needs attention. |
Revenue by Project Manager Break by Status | How is the reported revenue measure distributed across project managers and statuses? | Prepare an ownership review that considers both value and delivery condition. |
Before using these views in a financial discussion, agree on what the underlying values represent.
Value should be one consideration when prioritizing intervention—not the only one. Also consider the customer commitment, the effect of the blocked work, and the action required to move the project forward.
Find projects with overdue or blocked work
Overdue Tasks by Project
This chart counts tasks due before today that are not Done or Not Applicable, grouped by project and task status. It excludes tasks belonging to Pending, Done, Cancelled, or On Hold projects. GUIDEcx Knowledge Base
Important: An on-hold project can contribute to Total Active Projects while its tasks are excluded from Overdue Tasks by Project. These widgets use different scopes.
Use the chart to identify where overdue work is concentrated, then inspect the tasks involved.
A project with several overdue tasks may need a different response depending on whether the work is progressing, awaiting a decision, or blocked. Review the underlying tasks before assigning a cause.
Projects with the most stuck tasks
#10 Projects with Most Stuck Tasks ranks active projects by their current Stuck task count, showing up to 10 projects. GUIDEcx Knowledge Base
This view includes on-hold projects within its active-project scope.
Use it to prepare a focused discussion about blocked work. For each project, identify what is preventing progress, who needs to act, and which customer commitment could be affected.
A high stuck-task count does not automatically establish the project’s priority. One blocked approval may have a greater effect on a go-live than several lower-impact tasks.
Understand the project drilldown
The drilldown provides project-level context for the report’s summary signals.
Start with the project and customer, then review the dates, status, summaries, and value information relevant to your investigation. The fields below are grouped by purpose rather than screen order.
Project identity and context
Field | What it shows |
Project Name | The project’s name. |
Customer Name | The customer associated with the project. |
Internal Summary | The internal summary recorded for the project. |
External Summary | The external summary recorded for the project. |
PM Member IDs | Member identifiers associated with the project’s project managers. |
Phase Names | Phase names associated with the project. |
Milestone Names | Milestone names associated with the project. |
Brand Names | Brand names associated with the project. |
Brand Is Retired | Whether the associated brand is marked as retired. |
Use phase and milestone names for context, then review the underlying project to establish its current delivery stage.
When preparing a customer conversation, review the external summary and confirm that the wording still reflects the project’s circumstances.
Project dates
Field | What it shows |
Start Date | The project’s start date. |
Due Date | The project’s due date. |
Forecasted End Date | The project’s forecasted finish date. |
Kicked Off At | The recorded kickoff timestamp. |
Created At | The recorded project creation timestamp. |
Updated At | The recorded project update timestamp. |
Project creation, scheduled start, kickoff, and expected finish are different points in the project lifecycle. Choose the date that matches the question you are investigating.
Do not use an update timestamp alone as evidence that all outstanding work has been reviewed.
Status and health
Field | What it shows |
Is Forecasted Late | Whether the record identifies the project as forecasted late. |
Is Forecasted Ahead | Whether the record identifies the project as forecasted ahead. |
Is Complete | The project’s completion indicator. |
Status Label | The project’s status label. |
Status Explanation | The explanation associated with the project’s status. |
Status Updated At | The timestamp associated with the status update. |
RAG Status | The project’s RAG health indicator. |
RAG Description | The explanation associated with the RAG assessment. |
RAG Updated At | The timestamp associated with the RAG update. |
Review explanatory fields alongside the indicators. Use them to prepare specific questions for the project manager rather than assuming a status or health indicator explains the entire situation.
Value and duration
Field | What it shows |
Cash Value | The value recorded in the project’s Cash Value field, populated by a user or automation. |
Billing Rate | The billing-rate value reported for the project. |
Duration Days | The project’s reported duration in working days. |
Planned Duration Days | The reported planned duration in working days. |
Forecasted Duration Days | The reported forecasted duration in working days. |
Forecasted Variance Days | The reported forecast variance in working days. |
Duration values use the workspace’s configured working days.
Review these values alongside the project’s dates. Before sharing a financial interpretation, confirm what your organization records as Cash Value and how the relevant billing information is configured.
Example: Prepare for a weekly portfolio review
The following is an illustrative Professional Services scenario.
An onboarding leader is preparing for a weekly review and wants the meeting to end with a focused set of delivery actions.
Choose the portfolio to review. Filter by project manager and the onboarding type recorded in a custom field. Include on-hold projects when the discussion needs to cover restart decisions.
Identify schedule concerns. Review Late Projects and Projects Forecasted Late, then consider which upcoming customer commitments need attention.
Investigate blocked or overdue work. Use the project charts and stuck-project view to choose projects for a closer review.
Review project context. Check the drilldown’s dates, summaries, status explanations, and available RAG information.
Agree on the next action. Open the underlying projects, confirm the outstanding work, and assign an action owner and follow-up date.
For one implementation, the team might decide to resolve a final approval before the next customer meeting. For an on-hold project, the useful outcome might instead be an agreed restart condition and a date to reassess the plan.
The report helps the team choose where to investigate. The project review determines what should happen next.
Best practices
These are suggested reporting practices rather than product requirements.
Use a consistent review cadence. Review the portfolio weekly, and revisit time-sensitive projects more frequently as customer commitments approach.
Compare similar work. Separate different onboarding types, customer segments, or delivery motions before comparing duration or value.
Prioritize impact, not only counts. Investigate what an overdue or stuck task prevents, especially when it affects an approval, migration, training session, or go-live.
Keep Cash Value consistent. Agree on what the field represents and check that manual entries and automation follow the same convention.
Finish with a decision. Record a clear action, owner, and follow-up date rather than leaving the meeting with a list of projects that need “more attention.”
Frequently asked questions
Why might a project appear in one widget but not another?
Widgets answer different questions and can use different inclusion rules.
For example, Total Active Projects includes on-hold projects, while Overdue Tasks by Project excludes their tasks. Check the widget’s scope and your selected filters before treating different results as an error.
What should I check when Cash Value does not match my expectations?
First, confirm that the report filters include the intended projects. Then review the Cash Value recorded on those projects.
Because the field can be populated manually or through automation, check the relevant entry process or configuration before deciding whether the report value is incorrect.
Can I use this report for a single customer?
Yes. Use the Customer filter to focus on a particular account.
Review the customer’s upcoming commitments, then use the project-level information to prepare specific questions and action items for the check-in.